Timeline changes

Active Travel Programme Timeline Changes

Edinburgh Council: October 2025 vs 03 Feb 2026. We flag projects where the construction start date moved later.

Starts delayed

30

Construction start moved later

Biggest delay

2y 5m

Cameron Toll to BioQuarter general scheme - Lady Road section

Ends delayed

29

Construction end moved later

New / missing

8 / 6

New in Feb / not listed in Feb

Sort
Red = laterGreen = earlierGrey = no changeDates are month-year from the council PDFs.
About this comparison

Projects are matched by name and phase. If a project was renamed between snapshots, it may show up as new or missing.

If something looks surprising, use the Open PDF buttons above to double-check the source.

Leith Connections

PhasePhase 2 - LTN
delayed start

October 2025

StartJan 2026toEndMay 2026

Construction for this project has not yet started.

03 Feb 2026

StartFeb 2026toEndApr 2026

Project is under construction

Delayed1m

One-way Street Exemptions

PhaseBatch 1
delayed start

October 2025

StartJan 2026toEndJul 2026

Construction for this project has not yet started.

03 Feb 2026

StartFeb 2026toEndApr 2026

Construction in progress

Delayed1m

QuietRoute 9

PhasePhase 2. Site C
delayed start

October 2025

StartJan 2026toEndApr 2026

Construction for this project has not yet started.

03 Feb 2026

StartMar 2026toEndSep 2026

Construction for this project has not yet started

Delayed2m

Travelling Safely buildouts improvemen

PhasePhase 2: Morningside Road

October 2025

StartJun 2026toEndAug 2026

Construction for this project has not yet started.

03 Feb 2026

StartJun 2026toEndAug 2026

Construction for this project has not yet started

No change

QuietRoute 9

PhasePhase 2: Site B
delayed start

October 2025

StartJan 2026toEndApr 2026

Construction for this project has not yet started.

03 Feb 2026

StartJul 2026toEndSep 2026

Construction for this project has not yet started

Delayed6m

Bughtlin Burn Bridge

delayed start

October 2025

StartNov 2025toEndDec 2025

Construction for this project has not yet started.

03 Feb 2026

StartSep 2026toEndOct 2026

Construction for this project has not yet started

Delayed10m

Kingsknowe Park Crossing

delayed start

October 2025

StartNov 2025toEndDec 2025

Construction for this project has not yet started.

03 Feb 2026

StartSep 2026toEndOct 2026

Construction for this project has not yet started

Delayed10m

Roseburn Path – Union Canal

PhaseDuff Street Lane Access Con
delayed start

October 2025

StartApr 2026toEndJul 2026

Construction for this project has not yet started.

03 Feb 2026

StartOct 2026toEndDec 2026

Construction for this project has not yet started

Delayed6m

Secure On-street Cycle Parking

PhasePhase 2: 162 units (TRO) Sta
delayed start

October 2025

StartJul 2026toEndNov 2026

Construction for this project has not yet started.

03 Feb 2026

StartOct 2026toEndNov 2026

Construction for this project has not yet started

Delayed3m

Fillyside Crossing

delayed start

October 2025

StartAug 2026toEndSep 2026

Construction for this project has not yet started.

03 Feb 2026

StartNov 2026toEndDec 2026

Construction for this project has not yet started

Delayed3m

Cameron Toll to BioQuarter general scheme

delayed start

October 2025

StartSep 2026toEndApr 2027

Construction for this project has not yet started.

03 Feb 2026

StartDec 2026toEndOct 2027

Construction for this project has not yet started

Delayed3m

Secure On-street Cycle Parking

PhasePhase 3
delayed start

October 2025

StartNov 2026toEndJan 2027

Construction for this project has not yet started.

03 Feb 2026

StartFeb 2027toEndApr 2027

Construction not yet started

Delayed3m

Lothian Road

October 2025

StartMar 2027toEndMar 2028

Construction for this project has not yet started.

03 Feb 2026

StartMar 2027toEndMar 2028

Construction for this project has not yet started

No change

Meadows to George Street

delayed start

October 2025

StartJan 2027toEndMay 2028

Construction for this project has not yet started.

03 Feb 2026

StartMar 2027toEndAug 2028

Construction for this project has not yet started

Delayed2m

One-way Street Exemptions

PhaseBatches 3, 4 & 5
delayed start

October 2025

StartJul 2026toEndSep 2026

Construction for this project has not yet started.

03 Feb 2026

StartMar 2027toEndMay 2027

Construction for this project has not yet started

Delayed8m

QuietRoute 30 - Dalkeith Road to Ratcliffe Terrace

delayed start

October 2025

StartJun 2026toEndNov 2026

Construction for this project has not yet started.

03 Feb 2026

StartMar 2027toEndMay 2027

Construction for this project has not yet started

Delayed9m

Smokey Brae

delayed start

October 2025

StartOct 2026toEndApr 2027

Construction for this project has not yet started.

03 Feb 2026

StartMar 2027toEndAug 2027

Construction for this project has not yet started

Delayed5m

Meadows to Union Canal

PhasePhase 1 of the General Proje
delayed start

October 2025

StartDec 2026toEndApr 2027

Construction for this project has not yet started.

03 Feb 2026

StartApr 2027toEndNov 2027

Construction for this project has not yet started

Delayed4m

Rural Speed Limits

delayed start

October 2025

StartNov 2026toEndJan 2027

Construction for this project has not yet started.

03 Feb 2026

StartApr 2027toEndJun 2027

Construction for this project has not yet started

Delayed5m

Queensferry Connections

delayed start

October 2025

StartJan 2027toEndMar 2028

Construction for this project has not yet started.

03 Feb 2026

StartMay 2027toEndJul 2029

Construction for this project has not yet started

Delayed4m

Longstone Link

PhasePhase 1 – Bridge
delayed start

October 2025

StartApr 2027toEndFeb 2028

Construction for this project has not yet started.

03 Feb 2026

StartJun 2027toEndMay 2028

Construction for this project has not yet started

Delayed2m

LDPAP - Leith Connections

PhasePhase 3
delayed start

October 2025

StartApr 2027toEndAug 2028

Construction for this project has not yet started.

03 Feb 2026

StartJul 2027toEndDec 2028

Construction for this project has not yet started

Delayed3m

St Andrew Square

October 2025

StartSep 2027toEndJan 2028

Construction for this project has not yet started.

03 Feb 2026

StartAug 2027toEndFeb 2028

Construction for this project has not yet started

Earlier1m

Dalry Town Centre

PhaseDalry Town Centre
delayed start

October 2025

StartJul 2027toEndJul 2028

Construction for this project has not yet started.

03 Feb 2026

StartSep 2027toEndMay 2028

Construction for this project has not yet started

Delayed2m

Granton Liveable Neighbourhood

PhaseGeneral

October 2025

StartJan 2028toEndApr 2028

Construction for this project has not yet started.

03 Feb 2026

StartSep 2027toEndNov 2027

Construction for this project has not yet started

Earlier4m

NEAT Connections

delayed start

October 2025

StartJun 2027toEndNov 2028

Construction for this project has not yet started.

03 Feb 2026

StartSep 2027toEndSep 2028

Construction for this project has not yet started

Delayed3m

Currie and Balerno Active Travel Improvements

October 2025

StartOct 2027toEndDec 2027

Construction for this project has not yet started.

03 Feb 2026

StartOct 2027toEndJan 2028

Construction for this project has not yet started

No change

George Street to Waverley Bridge

delayed start

October 2025

StartNov 2027toEndNov 2028

Construction for this project has not yet started.

03 Feb 2026

StartDec 2027toEndDec 2028

Construction for this project has not yet started

Delayed1m

Barnton And Whitehouse Road Link To Ncn1

delayed start

October 2025

StartNov 2027toEndOct 2028

Construction for this project has not yet started.

03 Feb 2026

StartJan 2028toEndJun 2029

Construction for this project has not yet started

Delayed2m

Fountainbridge - Dundee Street

October 2025

StartJan 2028toEndMar 2028

Construction for this project has not yet started.

03 Feb 2026

StartJan 2028toEndMar 2028

Construction for this project has not yet started

No change

George Street and First New Town

delayed start

October 2025

StartJan 2028toEndOct 2029

Construction for this project has not yet started.

03 Feb 2026

StartMar 2028toEndFeb 2030

Construction for this project has not yet started

Delayed2m

Niddrie Mains Road

October 2025

StartSep 2028toEndJan 2029

Construction for this project has not yet started.

03 Feb 2026

StartMay 2028toEndAug 2029

Construction for this project has not yet started

Earlier4m

Cameron Toll to BioQuarter general scheme

PhaseLady Road section
delayed start

October 2025

StartAug 2026toEndOct 2026

Construction for this project has not yet started.

03 Feb 2026

StartJan 2029toEndApr 2029

Construction for this project has not yet started

Delayed2y 5m

Roseburn to Union Canal Phase 2

PhaseGeneral
delayed start

October 2025

StartDec 2028toEndMar 2029

Construction for this project has not yet started.

03 Feb 2026

StartMay 2029toEndAug 2029

Construction for this project has not yet started

Delayed5m

Charlotte Square

PhasePhase 3. Permanent Scheme
delayed start

October 2025

StartJul 2028toEndJun 2029

Construction for this project has not yet started.

03 Feb 2026

StartOct 2029toEndOct 2030

Construction for this project has not yet started

Delayed1y 3m

Meadows to Union Canal

PhaseKings Theatre

October 2025

StartJan 2026toEndApr 2026

Construction for this project has not yet started.

03 Feb 2026

StartJan 2026toEndApr 2026

Project is under construction

No change

Corstorphine Low Traffic Neighbourhood

delayed start

October 2025

StartNov 2025toEndJan 2026

Construction for this project has not yet started.

03 Feb 2026

StartDec 2025toEndMar 2026

Project is under construction

Delayed1m

Dalry Town Centre

PhaseDalry Side Street Project
delayed start

October 2025

StartNov 2025toEndMar 2026

This project is under construction.

03 Feb 2026

StartDec 2025toEndMar 2026

Project is under construction

Delayed1m

Secure On-street Cycle Parking

PhasePhase 2: 162 units (TRO) Sta

October 2025

StartNov 2025toEndNov 2026

Construction for this project has not yet started.

03 Feb 2026

StartNov 2025toEndFeb 2026

Project is under construction

No change

West Edinburgh Link

PhasePhase 1 of Construction - Ba

October 2025

StartNov 2025toEndJul 2029

Construction for this project has not yet started.

03 Feb 2026

StartNov 2025toEndJun 2026

Project is under construction

No change

Silverknowes Rd TS

October 2025

StartNov 2025toEndJan 2026

Construction for this project has not yet started.

03 Feb 2026

StartAug 2025toEndMay 2026

Project is under construction

Earlier3m

Travelling Safely buildouts improvemen

PhasePhase 1: Portobello and St J

October 2025

StartApr 2025toEndJun 2025

This project has been constructed.

03 Feb 2026

StartApr 2025toEndJun 2025

This project has been constructed.

No change

Lasswade Road

October 2025

StartNov 2024toEndJan 2025

This project has been constructed.

03 Feb 2026

StartNov 2024toEndJan 2025

This project has been constructed.

No change

Leith Connections

PhasePhase 1a - Strategic Route

October 2025

StartNov 2024toEndDec 2025

This project is under construction.

03 Feb 2026

StartNov 2024toEndDec 2025

This project has been constructed.

No change

Deanhaugh Street and Leslie Place

October 2025

StartOct 2024toEndJul 2025

This project has been constructed.

03 Feb 2026

StartOct 2024toEndDec 2024

This project has been constructed.

No change

Charlotte Square

PhasePhase 2. Interim Scheme

October 2025

StartJun 2024toEndOct 2025

This project is under construction.

03 Feb 2026

StartJun 2024toEndMar 2026

Project is under construction

No change

Melville Crescent

October 2025

StartApr 2024toEndDec 2024

This project has been constructed.

03 Feb 2026

StartApr 2024toEndDec 2024

This project has been constructed.

No change

QuietRoute 60 – Davidson's Mains Park Ph 2

October 2025

StartApr 2024toEndMar 2025

This project has been constructed.

03 Feb 2026

StartApr 2024toEndMar 2025

This project has been constructed.

No change

London Road

October 2025

StartApr 2023toEndMar 2024

This project has been constructed.

03 Feb 2026

StartApr 2023toEndMar 2024

This project has been constructed.

No change

Tram Safety Improvements

October 2025

StartApr 2023toEndMar 2024

This project has been constructed.

03 Feb 2026

StartApr 2023toEndMar 2024

This project has been constructed.

No change

Roseburn Path – Union Canal

PhaseDalry Road Toucan Installatio

October 2025

StartFeb 2025toEndMar 2025

This project has been constructed.

03 Feb 2026

StartMar 2023toEndFeb 2025

This project has been constructed.

Earlier1y 11m

Roseburn Path – Union Canal

PhaseR2UC General

October 2025

StartMar 2023toEndFeb 2025

This project has been constructed.

03 Feb 2026

StartMar 2023toEndFeb 2025

This project has been constructed.

No change

City Centre West East Link

October 2025

StartFeb 2022toEndFeb 2025

This project has been constructed.

03 Feb 2026

StartFeb 2022toEndFeb 2025

This project has been constructed.

No change